THE INDUSTRIAL COURT’S JURISDICTION IN DETERMING CLAIMS REGARDING CONTRACTS WITH ARBITRATION CLAUSES: A CASE REVIEW OF GIORGIO ZENEGALI VS. SARI CONSULTING LTD. (LABOUR DISPUTE REFERENCE NO. 299 OF 2019).
Introduction.
Arbitration clauses are
a common feature in different kinds of contracts, as a dispute resolution
mechanism in case of any hiccups during the execution of the contract. Usually,
where parties have agreed to arbitration as the dispute resolution mechanism, it
is mandatory and the parties cannot then go to the courts of law on first
instance to resolve the dispute except where the arbitration clause is null and
void. In other words, the courts of law would have no jurisdiction to entertain
a dispute where the parties agreed to arbitration as the dispute resolution
mechanism.
However, where it comes
to matters relating to employment (contracts of or for services), the
Industrial Court of Uganda has held that an arbitration clause notwithstanding,
the Industrial Court still has jurisdiction over disputes arising from
employment related matters.
This blog reviews the
Industrial Court’s ruling in Giorgio
Zenegali v Sari Consulting Ltd (Labour Dispute Reference No. 299 of 2019) on
its jurisdiction in employment disputes regarding contracts with arbitration
clauses.
Brief
Facts.
The Claimant, Giorgio
Zenegalia, was an employee of the respondent, Sari Consulting Ltd under a
contract that provided for a dispute resolution mechanism of arbitration and
conciliation under the rules of the Chamber of Commerce of Rome and in
accordance with the Italian Law and Language. The claimant’s claim in the
Industrial Court was for unpaid salary arrears and other benefits as agreed and
breach of contract. The respondent raised a preliminary objection that on the
basis of the contract between the parties, the Industrial Court had no
jurisdiction to entertain the dispute since the Employment Act was not
applicable to the contract as the parties had chosen mandatory arbitration to
be done in Rome as provided for under clause 8 of the contract of service.
Relying on Section 91 of the Evidence Act and Section
5 and 40 of the Arbitration and Conciliation Act, the Counsel for the Respondent
strongly submitted that jurisdiction being a creature of statute, the
Industrial Court could not entertain the claim because in clause 10 of the
respective contracts, the parties surrendered to Italian Law. He argued that
except by mutual agreement of both parties, neither of them could run away from
the binding terms of the agreement.
The Claimant on the
other hand argued that Section 12(1) and
(2) of the Employment Act and Section 8(1)(a) of the Labour Dispute
(Arbitration and Settlement) Act as amended, both the Labour Officer and
the Industrial Court are granted jurisdiction to entertain employment disputes.
He argued that reliability on an exclusive clause in the contract was aimed at
evading liability under the Contract. He relied on the decision in CMA Cam Uganda Ltd vs. M/S Sekatawa International
Ltd (Civil Appeal No. 27/2013) which held that courts in Uganda have jurisdiction by virtue of the fact that the
contract was performed in Uganda and that one of the circumstances which could
be considered in establishing whether court could exercise jurisdiction was
whether the defendant genuinely desired trial in a foreign country or was only
seeking procedural advantages.
The
Claimant submitted that the defendant in this case was only seeking procedural
advantage as there was no plausible reason to have the matter tried in Italy.
Decision
of the Court.
The Court acknowledged
that parties have freedom to contract and once they reduce the contract in
writing, they are bound by the provisions of the Contract so reduced in
writing. Court further acknowledged that in interpreting the contract so
reduced in writing, the courts have to take into account the intention of the
parties at the time the contract was signed as well as the law prevailing at
the time the contract was made but also at the time the court is making the
decision.
Court however pointed out that Section 9 of the Labour Dispute
(Arbitration & Settlement) Act 2006 as now amended states that:
“The Arbitration and Conciliation Act shall
not apply to any proceedings of the Industrial
Court under this Act, or to any award made by the Industrial Court.”
Court therefore opined
that the law since the Labour Dispute
(Arbitration & Settlement Act) as the law that gives jurisdiction to the
Industrial Court ousts the application of the Arbitration and Conciliation Act
by the industrial Court, the Act could not apply in the circumstances and as
such, the Industrial Court was not bound or obliged to refer the matter to
arbitration under the said Arbitration and Conciliation Act.
While it was clear that
the parties intended their dispute to be resolved outside the jurisdiction of
the Industrial Court, court pointed out that the question for determination is whether the exclusion of the
jurisdiction of the courts in Contract would automatically oust court’s
jurisdiction. To answer this question, court relied on the decision in Huadar Guangdong Chinese Co. Ltd vs. Dance
Logistics Uganda Limited (Civil Suit No. 4/2012) where court held:
“It is settled law that a simple clause in
an enforceable contract does not oust the
unlimited jurisdiction of the
High Court as conferred to it by the Supreme law of the land.”
As a court equipped
with the same jurisdiction as the High Court, the arbitration clauses in the
contracts could not oust its jurisdiction over employment matters.
The Court also found
that the expenses likely to be incurred
when a matter was to be handled outside the domestic jurisdiction would be a
factor to consider in determining the question of jurisdiction embedded in a
contract.
Court held that Section 5 of the Labour Dispute
(Arbitration and Settlement) Act and Section 12 and 13 of the Employment Act
grant the Industrial Court and Labour Officer respectively, jurisdiction to
handle employment disputes. Court concluded that given the huge expenses that would be incurred by the respondent if the
claim was referred to Rome in accordance with the contract, and given that no
special and reasonable explanation was given to the Court for such expensive
expedition, the respondent was merely
seeking procedural advantage intended to halt the progress of the claim
under the contract of service and this is unacceptable in light of Section 27
of the Employment Act which allows for application by agreement between parties
of terms and conditions that are more favourable to the employee than those contained in the
Act.
Conclusion.
From this decision, it
is clear that the position of the law regarding the Industrial Court’s
jurisdiction is adjudicating disputes regarding employment contracts with
mandatory arbitration clauses is thus:
- 1. The Labour Dispute (Arbitration & Settlement Act) as the law that gives jurisdiction to the Industrial Court ousts the application of the Arbitration and Conciliation Act by the industrial Court and as such, the Industrial Court is not bound or obliged to refer matters to arbitration under Arbitration and Conciliation Act. The Industrial Court has jurisdiction to preside over such matters.
- 2. The exclusion of the jurisdiction of the courts in Contract does not automatically oust court’s jurisdiction and as such, a simple clause (even of mandatory arbitration) in an enforceable contract does not oust the jurisdiction of the Industrial Court over employment matters.
- 3. The
expense likely to be incurred in resolving a dispute outside the domestic
jurisdiction will be a factor to be considered where the court is determining
whether it can exercise jurisdiction over the dispute.
Conclusively, regarding
employment matters, the Industrial Court has jurisdiction to handle disputes
arising therefrom regardless of whether there is a clause on mandatory arbitration
or not, especially where arbitration would be more costly.
Comments
Post a Comment